Let there be a ROOF! (and what it looks like after 3" plus of rain w/out one)

Sunday we picked up 2000 SF of hard Wisconsin maple flooring that will cover the majority of the main floor.  We also had to clean up after the storms on Saturday which left the floor standing in water.  I expected to get to the site on Monday and have most of the floors drying out but it stormed again on Sunday night.  Below you can see what happens when you have flooring material that doesn't simply absorb all that water but contains it.  We had 1 1/2" of water over most of the main floor and more that had drained into the basement.  I spent about 3 hours in the morning sweeping/squeegeeing again.  While I was doing that the crew started roofing using the Zip roof system - the interesting thing about this is that the seams are not clipped nor are they toungue and groove.  Once the sheets are all down you tape the seams using an uber-strong tape.  To bond it well you then roll it with a special roller.  The sample rolled well during the demo was very hard to remove while that not rolled wasn't that difficult.  This flooring and roofing is warranted to be waterproof for 6 months and 10 months respectively without any other protection.  Pretty impressive.

Today the crew finished the clerestory roof section and walled up the East end of the house.  We still have to wait for the well drilling rig to get behind the house before we can put up the deck and finish the framing and sheathing of the roof.  We hope to be able to do that starting Friday but a lot depends on weather and if the soil is loose/muddy on Friday when the drilling rig arrives.
Here's the flooring after cleaning up some of the standing water on Monday morning

more of the water

and yet more..

the last view with water!


The back of the house with all roof sheathing (except the unbuilt deck) installed

The guys woking on the clerestory overhang.



This is the drive view at the end of the day on Tuesday - notice the shadow on the West end which will be he covered deck.  Perfect!  you should also be able to see the small bump in the roof over the front door which is the installed skylight.  It reflects the clerestory roof in miniature.  As the crew says No mas agua!

Monday, August 1, 2011

Start of the roofline, more about water, and a stairwell (at least part of it)

Last week marked the completion of framing the walls in the basement and the floor sheathing on the main floor.  Friday a large part of the lumber was delivered for the main floor framing and roof structure and then Saturday a hack of 2s8x10's was dropped.  This morning the site looked like a lumber yard (especially after we picked up another 100 2x4x16's) and lunchtime marked the start of the installation of the roof support BCIs.

That's the roof lumber on the truck - the long BCIs on the top will make up the roof that extends from the edge of the back deck up and over the clarestory.

This is the lumber all lined up ready to be made into stud-walls and a roof


One more check of the plans - from the vantage point of the top of the 10" wall!


This is the first BCI to be installed.   There's a gusset installed at the peak to provide additional strength.  




This shows the East end view of the house with the roofline defined by this BCI system.


This is the landing for the stairwell - that's a floor to almost ceiling window providing a great view of the forest behind the house.



And then there were two BCI beams installed.


This gives you an ideal of the view from driveway as you approach the house.


This is the inside view (West to East) at the end of the day.  You can see the shading provided by the trees on the floor system  so overheating from the setting sun will be minimized during the summer months.


We received the information on the fracking today.  Fracking is essentiall as expensive as drilling another well (but not to 606 feet) and the success rate is a great 99%. The downside is that success is to get to 1 GPM flow rate.  Using the basic calculation of 500' of storage in the 6" pipe with about 1.4 gallons of storage per foot we'd have about 750 gallons in a reservoir column but there are those who say fracking is only a short-term option.  We're still considering this option but there's clearly a difference of opinions on the utility of this option.
  We have some information on geothermal heating (ground source heat pump - which is different than "heat pumps" of the normal vernacular is you use the ground as the heat exhanger for the heating/cooling loops).  We would need to drill one more well for the geothermal and then one for the water.

Our other possibility for water is connecting to the county water lines which are about 1000' from the house.  The problem with this is we would require an easement across an adjacent property to get to the water lines.  We know the connection and tap fees which sum up to about 1/2 the cost of the well and that doesn't include running the line from the closest county water line to the house (including the trench digging), or the cost of the legal consultation for the easement (and remuneration of the property owner for the easement if requested).

  This is a tough decision on the water and geothermal but due to tax credits available there may be a financial benefit over going with our minisplits.  We hoped all along to eliminate ductwork but between Federal and State tax rebates, you save some 65% of the cost of the installation - that still doesn't get it below the cost of mini-splits but it definitely helps reduce the impact of a dry well.

Standing in the doorway at the West end of the house this afternoon we could once again feel the "cool" breeze coming though the house.  The other thing that was remarkable was how cool the basement was with only a layer of sheathing on it and the temperature outside was approaching 95 degrees.  It will clearly be great to see the temperatures when the additional insulation is installed, the doors and windows are in, and the R-60 roof system is up.  We may not need to run that ground-soturce heat pump very much at all!

Monday, July 25, 2011

The start of the framing

Today the Rodriguez Builders crew started working on the framing for the basement walls which will also support the flooring for the main floor.  We had a slight delay due to finding mold on a rack of studs - Kevin made a quick run to Lowes to get enough to keep the crew working pending the replacement from the supply house.  They got the entire East end of house lapped with the 2x4 stud wall and were working on the load-bearing walls and interior walls when I left at about 2:45.  Once again the thunderstorms were broiling around the site - no rain by the time I left but it was threatening and it did rain with some pretty heavy thunder when I stopped at Lowes on the way home - which is about 10 miles from the site.

Here's what it looked like at the start of the day - Burlap is still on the slab to allow it to dry. 
This is the stud wall on the North and East walls.  

This and the next photo provide proof that this house is due south facing.  Note the shadows on those lugs for the deck - they're  nearly vertical and only because it's 1:19 are they slightly off.  I also like this picture because it shows the family room door and window wall that will be our view to the woods and intermittent stream to the south of the house.

More proof of Southerly orientation of the majority of the glass.  

I took this picture because I liked the perspective it provides from the South East corner of the clearing.   The dirt pile I'm standing on while taking this picture will be used for backfill of the foundation once the flooring system is installed.  


This is another picture of the South wall of the house - note the LVLs and TJIs stacked ready for the flooring to be installed in the next couple of days.